Regional Transportation Extension Projects
The Measure C Regional Program addresses county-wide transportation needs. It is split into urban and rural subprograms with priority projects on state highways and major city and county roads.
Today, seven urban and nine rural projects are finished. Nine others are in different stages of development. Approximately $391.5 million has been equally split between urban and rural projects.

Image description
A map displaying the Measure “C” Short-Term Regional Transportation Program for Urban Area Tier 1 projects in Fresno County. The title “Urban Area Projects Tier 1” is prominently featured at the top. The map outlines planned transportation infrastructure improvements with color-coded symbols indicating the construction delivery year, ranging from prior to 2017 to beyond 2023/24. Key features include the Fresno and Clovis metropolitan areas, spheres of influence, incorporated areas, and major roadways. The legend provides details on project timelines and geographic classifications.

Image description
This image is a map titled “Rural Area Projects Tier 1,” displaying planned and completed street and highway projects under Measure “C” in Fresno County. The map is part of the Short-Term Regional Transportation Program and highlights Rural Area Tier 1 projects, color-coded by their construction delivery year.
The map covers various locations across Fresno County, including cities like Clovis, Fresno, Kerman, Selma, Kingsburg, and Huron. Major highways and roads are marked along with project locations designated by labeled circles.
A legend at the bottom indicates the project timeline:
- Projects completed prior to 2017/18 (green)
- 2017/18 projects (orange)
- 2018/19 projects (red)
- 2019/20 projects (blue)
- 2020/21 projects (yellow)
- 2021/22 projects (pink)
- 2022/23 projects (purple)
- 2023/24 projects (black)
- Future projects beyond FY 2023/24 (white)
Additionally, a red dashed line in the northeast corner indicates that the Fresno County boundary extends further northeast beyond the visible map area. A compass in the lower left corner provides orientation, and a note states that the map is not to scale.
Tier 1 Projects
SR 180 East Seg II
SR 180 East Seg II ID: A
Project Description
New multi-lane Freeway on State Route 180 East from Clovis to Temperance. This project is a holdover from the Original Measure C Expenditure Plan.
Funding
Measure C Extension
$27.58 Million
STIP
$60.13 Million
State Taxes
$20 Million
Total Cost
$107.7 Million
Progress
PROJECT COMPLETED (Construction began March 2008 and was completed in November 2010.)
SR 180 West Seg II (Brawley to Hughes/West)
SR 180 West Seg II (Brawley to Hughes/West) ID: B
Project Description
Three phase project.
B1 – New Freeway on SR 180 West from Brawley to Hughes West.
B2 – Frontage Road (Realign Ronquio Blvd)
B3 – Landscaping & Irrigation.
Funding
Original Measure C38 Million
$38 Million
SLPP
$2.21 Million
STIP
$5.45 Million
RTMF
$0.55 Million
Measure C Extension
$5.31 Million
Total Cost
$83.1 Million
Progress
Phase B1 – Completed 12/08
Phase B2 – Completed
Phase B3 – Scheduled
Phase B1
Phase Description
New Freeway on SR 180 West from Brawley to Hughes West.
Funding
Original Measure C
$38 Million
Total Phase Cost
$38M
Progress
Phase Completed – 12/08
Phase B2
Phase Description
Construct Frontage Road, Realign Ronquio Blvd and Install Traffic Signal
Funding
Measure C Extension
$5.31 Million
SLPP
$2.21 Million
Total Phase Cost
$7.519M
Progress
Phase Completed – 2015
Phase B3
Phase Description
Install Landscaping & Irrigation on the new freeway from Brawley to Teilman Avenue (Hughes/West Connector).
Funding
RTMF
$0.55 Million
STIP
$4.57 Million
Total Phase Cost
$5.122M
Progress
Design –
Completed (2012)
Right of Way –
Completed (2013)
Construction –
In-Progress: 2015-2021
SR41/168/180
SR41/168/180 ID: C
Project Description
New Braided Ramps adding capacity for safe connection between State Routes 41, 168 & 180. Funding accelerated with Measure C Extension and State Highway Operation & Protection Program – Mobility (SHOPP). One of the first Design/Build projects approved.
Funding
State Taxes
$55 Million
Original Measure C
$12.7 Million
Progress
Due to cost savings the project has been accelerated and chosen as a Design/Build.
Begin 2011.
Amount Expended in FY 17/18: $223,325
Construction – Completed
Landscaping Plant Establishment – Ongoing
Willow Avenue Widening
Willow Avenue Widening ID: D
Project Description
On Willow Ave from Barstow to Copper Ave, complete to 6-Lane Divided Road and retrofit existing bike paths.
Funding
Measure C Extension
$15.38 Million
Federal Aid
$4.34 Million
State Taxes
$250,000
Local Development Fees
$3.75 Million
Total Cost
$23.713M
Progress
Project to be built in 10 phases.
Projected Completion – 2020
Phase D1
Phase Description
Construct 2nd & 3rd northbound lanes with median, landscaping from Shepperd to Copper Ave. and traffic signal at Perrin Avenue.
Funding
Measure C Extension
$6.35 Million
Local Development Fees
$1.59 Million
Progress
Design and ROW –
Begin: 2014
Construction –
Begin: 2015 | End: 2020
Phase D2
Phase Description
Construct outside travel lane on the East side of roadway, median and landscaping from Teague to Perrin Ave.
Funding
Measure C Extension:
$322 Million
Local Development Fees
$453,000
Total Phase Cost
$775,000
Progress
PHASE D2
COMPLETED 2009.
Phase D2A
Phase Description
Install traffic signal and intersection improvements at Willow and Shepherd Avenue.
Funding
Federal Aid
$1.78 Million
Local Development Fees
$312,000
Measure C Extension
$353 Million
Total Phase Cost
$2.446M
Progress
PHASE D2A COMPLETED –
Began: 2007
Ended: 2008
Phase D3
Phase Description
Construct outside travel lane on the East side of the roadway, sidewalk, street lights and landscaping from Alluvial for 1/4 mile.
Funding
Measure C Extension
$554 Million
Local Development Fees
$139,000
Progress
PHASE D3 COMPLETED –
Begin: 2011/2012 | End: 2018
Phase D4A
Phase Description
Construct South bound lane on West side of Roadway, median, curbs and landscaping from Teague to Shepherd Ave.
Funding
Measure C Extension
$289 Million
Local Development Fees
$72,000
Total Phase Cost
$361,000
Progress
PHASE D4A COMPLETED –
2009
Phase D4B
Phase Description
Widen to 3 Southbound lanes from Shepherd Avenue to Behymer Avenue.
Funding
Local Development Fees
$715,000
Measure C Extension
$2.86 Million
Progress
PHASE D4B COMPLETED –
Begin: 2009 | End: 2015
Phase D5
Phase Description
Widen to 3 Southbound lanes from Decatur Avenue to Shepherd Avenue.
Funding
Federal Aid
$2.56 Million
Measure C Extension
$1.34 Million
Progress
Design –
COMPLETED
ROW –
COMPLETED
Construction – COMPLETED 2016
Phase D6
Phase Description
Widen to 3 Southbound lanes form International Avenue to Copper Avenue.
Funding
Measure C Extension:
$571 Million
Local Development Fees
$143,000
Progress
Design –
2017
Construction –
Begin: 2017 | End: 2027
Phase D7
Phase Description
Widen to 3 Southbound lanes from Herndon Avenue to Alluvial Avenue.
Funding
Measure C Extension
$1.29 Million
Local Development Fees
$322,000
Progress
Design –
Begin: 2014 | End: 2015
ROW –
Begin: 2014 | End: 2015
Construction –
Begin: 2017 | End: 2027
Phase D8
Phase Description
Retrofit Willow Avenue to six lanes from Barstow Ave. to Herndon Ave., provide intersection improvements at Bullard Avenue and will also install bicycle paths. Project phase includes design, right of way purchase and construction.
Funding
State Taxes
$250,000
Measure C Extension
$1.45 Million
Progress
PHASE D8 COMPLETED
Design –
Completed
ROW –
Completed
Construction –
Completed 2015
Temperance Avenue
Temperance Avenue ID: E
Project Description
Widen Temperance Ave from Bullard to Shepherd Ave to a 4-Lane Divided Road.
Funding
SLPP
$2.03 Million
Federal Aid
$455,000
Measure C Extension
$3.14 Million
Total Cost
$5.624M
Progress
This project will be built in 3 segment phases.
Phase E1
Phase Description
Widen to 4-Lane divided expressway from the Enterprise Canal to Nees Avenue and install a traffic signal at Nees Avenue. This phase includes design, right-of-way and construction.
Funding
SLPP
$728,000
Measure C Extension
$1.44 Million
Progress
Design –
Completed
ROW –
Competed
Construction –
Completed 2015
Phase E2
Phase Description
Widen to a 4-Lane divided Expressway from Bullard Avenue to Herndon Avenue and install traffic signal at Sierra Avenue. This phase includes design and construction.
Funding
SLPP
$1.3 Million
Federal Aid
$101,000
Measure C Extension
$1.49 Million
Progress
Design –
Completed
Construction –
Completed 2015
Phase E3
Phase Description
Widen to a 4-Lane Expressway with sidewalk, street lights and landscaping from Nees to Shepherd Avenue with traffic signal at Shepherd Avenue. This phase includes design, right-of-way and construction.
Funding
Local Development Fees
$354,000
Measure C Extension
$215,000
Progress
Design –
Begin: 2012 | End: 2013
Construction –
Begin: 2013 | End: 2019
Ventura Boulevard
Ventura Boulevard ID: F
Project Description
Widen Ventura Boulevard from State Route 41 to State Route 99 to a 4-Lane Divided Road. This project includes design, right-of-way and construction.
Funding
Local Development Fees
$200 Million
Measure C Extension
$6.14 Million
Progress
Design – COMPLETED
ROW – Begin: 2011 | End: 2012
Construction – Begin: 2013 | End: 2027
SR99 Monterey Bridge Demolition
SR99 Monterey Bridge Demolition ID: G
Project Description
Demolish the Monterey Street Bridge in downtown Fresno from Broadway to Golden State Boulevard for safety reasons. Original scope was to retrofit bridge however after inspections it was deemed unsafe to repair and too costly to replace.
Funding
Measure C Extension
$1.6 Million
Progress
Construction – Completed
California Ave Widening
California Ave Widening ID: H
Project Description
Widen California Ave to a 4-Lane Divided Road from Ventura Ave to Fruit Ave. This project has been phased into two segments. The first segment is completed. The second segment will be funded in the Long-Term Regional Transportation Program (2017-2027).
Funding
Measure C Extension
$2.2 Million
Funding Source TBD
$12.6 Million
Progress
This project has been split into two segment phases.
Phase 1 – COMPLETED
Phase 2 – The funding and schedule of the 2nd Phase is set in the Long-Term Program which was under review by Fresno COG in 2014, and projected 2027 completion.
Phase H1
Phase Description
Widen California Avenue from West to Fruit Avenues to a 4-Lane Divided Arterial
Funding
Measure C Extension
$2.2 Million
Total Phase Cost
$2.2M
Progress
PHASE H1 –
COMPLETED
Phase H2
Phase Description
Widen California Avenue to a 4-Lane Divided Arterial Road from Fruit Avenue to Ventura Avenue.
Funding
Measure C Extension
$692 Million
Funding Source TBD
$12 Million
Progress
Design –
$692,000 done in 2018.
ROW and Construction of Phase H2 will be programmed in the Long-Term sub program. Review of the Long-Term program will began in Fresno COG in 2017 with estimated costs of $12 million.
Peach Ave Widening
Peach Ave Widening ID: I
Project Description
Widen Peach Ave to a 4-Lane Divided Road from State Route 180 to Jensen Ave. Total project costs $25.08M. This project is split into four phases. Phase I2A, I2B, I2C and I3. The ultimate project will widen Peach Ave from two to four lanes with median l
Funding
State Taxes
$867,000
Measure C Extension
$8.99 Million
SLPP
$3.65 Million
Local Development Fees
$2.91 Million
Progress
Phase I2A – Completed 2012
Phase I2B – Begin: 2010 | End: 2019
Phase I2C – Begin: 2017 | End: 2027
Phase I3 – Completed 2015
Phase I2A
Phase Description
Install a new traffic signal on Peach Avenue at Church Avenue
Funding
Measure C Extension
$250,000
State Taxes
$267,000
Progress
PHASE I2A COMPLETED –
Begin: 2011 | End: 2012
Phase I2B
Phase Description
Phase I2B will widen Peach Avenue from Butler Avenue to Church Avenue (SJV Railroad Crossing) from two lanes to four lanes with protected left-turn lanes, median landscaping, bike lanes and streetlights.
Funding
Measure C Extension
$682,000
Local Development Fees
$1.9 Million
Progress
Design –
Begin: 2010
ROW –
Begin: 2016
Construction –
Begin: 2017 | End: 2019
Phase I2C
Phase Description
Phase I2C will purchase Right-of-Way to widen Peach Avenue to 4 lanes between Jensen Avenue to Butler Avenue providing median landscaping, protected left-turn lanes, bike lanes, streetlights and traffic signal at Butler Avenue. This phase is for Right-of-
Funding
Local Development Fees
$1.01 Million
Funding Source TBD
$15.69 Million
Progress
Design –
Begin: 2017 | End: 2018
ROW –
Begin: 2017 | End: 2018
Construction –
End: 2027
Phase I3
Phase Description
I3 will Widen Peach Avenue to 4 Lanes from State Route 180 to Butler Avenue. It will also provide median landscaping, protected left-turn lanes, bike lanes, landscaping, streetlights and installation of new traffic signals at Huntington Boulevard. Total P
Funding
SLPP
$3.65 Million
Measure C Extension
$8.06 Million
State Taxes
$600,000
Progress
Project I3 –
COMPLETED
Design –
Begin: 2009
ROW –
Begin: 2010
Construction –
Begin: 2013 | End: 2015
SR41 Auxiliary Lane
SR41 Auxiliary Lane ID: J
Project Description
Widen State Route 41 and build Auxiliary Lanes and improve on/off ramps from Tulare Street to O Street. This project will be programmed in the Long-Term Regional Transportation Program.
Funding
Funding Source TBD:
$21.59 Million
Progress
Project J COMPLETED 2018
The funding and schedule for this project was set in the Long-Term Program, began review at Fresno COG in 2014.
Herndon Ave Widening
Herndon Ave Widening ID: K
Project Description
Complete the widening of Herndon Ave to a 6-Lane Divided Road from State Route 99 to De Wolf Ave and retrofit existing bike paths. This project has been divided into 12 segment phases with a total cost of $115.844M. $94.511M has yet to be programmed.
Funding
Measure C Extension
$9.6 Million
Federal Aid
$8.66 Million
Funding Source TBD
$94.51 Million
Local Development Fees
$2.82 Million
State Taxes
$295,000
Progress
This project was split into 12 segment phases. (As of 2010 Phase 4 has been dropped.)
Phases K8 and K9 and the construction portion of Phases K10 will be programmed in the Long-Term Sub Program (2010-2027).
Phase K01
Phase Description
This phase widened Herndon Ave to 6-lanes from Willow Ave to Clovis Ave. This phase also installed traffic signals, sidewalks, landscaping medians, street lights and curb and gutter work.
Funding
Measure C Extension
$646,000
State Taxes
$295,000
Federal Aid
$1.96 Million
Local Development Fees
$915,000
Original Measure C
$120,000
Progress
COMPLETED
Phase K02
Phase Description
Widen Herndon Ave to 6-Lanes from Clovis Avenue to Fowler Avenue providing dual left turn lanes, install traffic signals, sidewalks and medians curb and gutters.
Funding
Local Development Fees
$38,000
SLPP
$799,000
Measure C Extension
$1.23 Million
Total Phase Cost
$2.063 Million
Progress
PHASE K02 –
COMPLETED
Design –
Begin: 2009 | End: 2011
ROW –
Begin: 2009 | End: 2012
Construction –
Begin: 2013 | End: 2015
Phase K03
Phase Description
This phase will widen Herndon Avenue from Temperance Ave to DeWolf Ave, provide dual left-turn lanes, install traffic signals and sidwalks.
Funding
Measure C Extension
$9.92 Million
Local Development Fees
$2.48 Million
Total Phase Cost
$12.403 Million
Progress
Design –
Begin: 2015 | End: 2017
ROW –
Begin: 2016 | End: 2017
Construction –
Begin: 2017 | End: 2020
Phase K5A
Phase Description
Widen Herndon Avenue to 6-Lanes from Brawley Avenue to Valentine Avenue.
Funding
Local Development Fees
$15,000
Federal Aid
$1.77 Million
Measure C Extension
$1.17 Million
Total Phase Cost
$2.951 Million
Progress
PHASE K5A COMPLETED 2016
Design –
Begin: 2010 | End: 2012
ROW –
Begin: 2011 | End: 2012
Construction –
Begin: 2012 | End: 2016
Phase K5B
Phase Description
Widen East-Bound Herndon Avenue to 6-Lanes from Blythe Avenue to Brawley Avenue.
Funding
Measure C Extension
$1.12 Million
SLPP
$818,000
Total Phase Cost
$1.936 Million
Progress
PHASE K5B COMPLETED
Design/ROW/Construction –
Begin: 2012 | End: 2013
Phase K5C
Phase Description
Widen West-bound Herndon Avenue to 6-Lanes from Blythe Avenue to Brawley Avenue.
Funding
Measure C Extension
$108,000
Federal Aid
$820,000
Total Phase Cost
$928,000
Progress
Design –
Begin: 2013 | End: 2014
ROW –
Begin: 2014 | End: 2015
Construction –
Begin: 2015 | End: 2019
Phase K06
Phase Description
This phase widened Herndon Avenue from Valentine Avenue to Marks Avenue to 6-Lanes providing median landscaping.
Funding
Federal Aid
$2.13 Million
Measure C Extension
$807 Million
Total Phase Cost
$2.936 Million
Progress
PHASE K06 COMPLETED 2014
Phase K07
Phase Description
Widen Herndon Ave to 6-Lanes from SR99 to Weber Avenue and install dual left-turn lanes at Golden State Boulevard. THIS PHASE IS COMPLETED.
Funding
Measure C Extension
$996,000
Federal Aid
$4.53 Million
Total Phase Cost
$5.524 Million
Progress
PHASE K07 – COMPLETED 2012
Phase K08
Phase Description
This phase will be programmed in the Long-Term Regional Transportation Program (2017-2027). Funding costs is estimated at $26.365 Million. This project will widen the Herndon Avenue Undercrossing at SR99 to five lanes.
Funding
Funding Source TBD
$26.36 Million
Progress
Begin: 2017 | End: 2027
Phase K09
Phase Description
Construct a 6-Lane Underpass under the Union Pacific Rail Road Crossing located at Herndon and Weber Avenues.
Funding
Funding Source TBD
$61.37 Million
Progress
This phase will be programmed in the Long-Term Program (2017-2027).
Phase K10
Phase Description
Widen Herndon Ave to 6-Lanes from Weber Ave to Polk Ave. The Design portion of this phase in programmed in the Regional Transportation Short Term Program. The Construction portion of this phase will be programmed in the Long-Term Program (2017-2027).
Funding
Measure C Extension
$5.42 Million
Local Development Fees
$1.36 Million
Progress
Design –
Begin: 2017 | End: 2018
The funding and schedule for Construction will be set in the Long-Term Program which began review at COG in 2015, set for 2021 completion.
Phase K11
Phase Description
Widen BNSF Rail Road Overpass to 6-Lanes. The Design only portion of this phase ($858,000) is programmed in the Short-Term Regional Transportation Program and the Right-of-Way and Construction will be programmed in the Long-Term Program.
Funding
Local Development Fees
$1.5 Million
Measure C Extension
$6.39 Million
Progress
Design –
Begin: 2012 | End: 2016
ROW & Construction –
Begin: TBD | End: 2023
Shaw Ave Upgrades
Shaw Ave Upgrades ID: L
Project Description
Improve Shaw Ave from Sunnyside to McCall to 6-Lane Divided Road upgrading traffic signals and grade crossings.
Funding
Local Development Fees
$2.45 Million
Measure C Extension
$9.82 Million
Progress
This project has been split into 2 segment phases in the Short-Term Sub Program.
Phase L1
Phase Description
Widen to a 6-Lane divided Expressway, street lights sidewalk and traffic signal from Local to DeWolf Avenue.
Funding
Local Development Fees
$387,000
Measure C Extension
$1.55 Million
Progress
Design –
Begin: 2011 | End: 2013
ROW –
Begin: 2011 | End: 2013
Construction –
Begin: 2013 | End: 2020
Phase L2
Phase Description
Widen to a 6-Lane divided Expressway, install outside travel lane, street lights, median, landscaping and undercrossing from DeWolf to McCall Avenue
Funding
Measure C Extension
$8.27 Million
Local Development Fees
$2.07 Million
Progress
Design –
Begin: 2012 | End: 2014
ROW –
Begin: 2014 | End: 2015
Construction –
Begin: 2014 | End: 2020
SR 99 Interchanges
SR 99 Interchanges ID: M
Project Description
Improve State Route 99 Interchanges at North and Cedar Avenues. This project will be funded in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$81.61 Million
Progress
The funding and schedule for this project will be programmed in the Long-Term Sub Program was under review at COG in 2014. Project Schedule 2024.
Veterans Boulevard
Veterans Boulevard ID: N
Project Description
This project has been split into two segment phases. Phase 1 covers Design/ROW of a Freeway Interchange & Grade Separation at UPRR crossing & Golden State Blvd. Phase 2 will connect the Interchange to Shaw & Herndon and will be funded in the Long Term Program.
Funding
Original Measure C
$8.84 Million
Measure C Extension
$3.25 Million
RTMF
$4.26 Million
STIP
$14.87 Million
Local Development Fees
$500,000
Progress
Phase 1. Design – Begin: 2008 | End: 2011
Phase 1. ROW – Begin: 2016 | End: 2020
Phase 2. Design – Begin: 2010 | End: 2012
Phase 2. ROW – Begin: 2016 | End: 2020
Construction for both phases to be programmed in the Long-Term Program (2017-2027).
Phase N1
Phase Description
Design of Veterans Boulevard to its ultimate six-lanes between Barstow Ave and Bullard Ave, with a new Over Crossing of SR 99 a bridge spanning Golden State Blvd, at grade separation of rail road crossing; 4-lanes from Bullard to Herndon & Barstow to Shaw
Funding
Original Measure C
$12.09 Million
RTMF
$4.26 Million
STIP
$14.87 Million
Progress
Phase N1 is Design and ROW only.
Design –
Begin: 2008 | End: 2011
ROW –
Begin: 2016 | End: 2017
Construction to begin in Long-Term Program (2017-2027).
Amount Expended in FY 17/18: $223,325
Phase N2
Phase Description
Phase N2 will Connect SR99 Interchange to Shaw & Herndon Avenues with 4-lanes from Bullard to Herndon and Barstow to Shaw. The project will include traffic signals at SR99 at Shaw, Bullard & Herndon Avenues & the Golden State Blvd connector roadway.
Funding
Local Development Fees
$2.61 Million
Original Measure C:
$765,000
Progress
Design –
Begin: 2010 | End: 2012
ROW –
Begin: 2016 | End: 2017
Construction to be programmed in the Long-Term Program (2017-2027).
SR 180 West
SR 180 West ID: A
Project Description
Create passing lanes in each direction on State Route 180 West (Whitesbridge Road) from Yuba Ave to James Ave.
Funding
Measure C Extension
$12.28 Million
Progress
Project A COMPLETED 2018
Design – Completed
Right of Way (ROW) – Begin: 2012 | End: 2013
Construction – Begin: 2013 | End: 2018
SR 180 East Seg III
SR 180 East Seg III ID: B
Project Description
Widen State Route 180 East from Temperance to Academy Ave to a 4-Lane Divided Expressway.
Funding
Federal Aid
$19.61 Million
STIP
$28.27 Million
Original Measure C
$30.56 Million
Total Cost
$78.443M
Progress
PROJECT COMPLETED.
Original Measure C Program Funds.
This project was accelerated using Original Measure C funds and leveraging Federal Stimulus ARRP funds.
Began: 2009 | Completed: 2011
SR 180 East Seg IV
SR 180 East Seg IV ID: C
Project Description
Widen State Route 180 East from Academy to Trimmer Springs to a 2-Lane Expressway on 4-Lane right-of-way. This project has been accelerated using Original Measure, State and Local Partnership and Extension Measure Regional Transportation Mitigation Fee
Funding
Measure C Extension
$9.44 Million
RTMF
$3.47 Million
Original Measure C
$13.13 Million
SLPP
$11.55 Million
Progress
Project C COMPLETED 2013
Part of the Original Measure C Program.
Design – Completed
ROW – Completed
Construction phase accelerated to began in 2013. Amount Expended in FY 17/18: $6,300
SR 180 East Seg V
SR 180 East Seg V ID: D
Project Description
Widen SR180 East to a 2-Lane Expressway from Trimmer Springs to Frankwood Avenue. The Design and part of the Right of Way portion of this project was accelerated using $13.589 Original Measure funds.
Funding
STIP
$57.76 Million
Original Measure C
$13.59 Million
Measure C Extension
$19.6 Million
Total Cost
$90.948M
Progress
Part of the Original Measure C Program.
Design – In Progress
ROW – In Progress
Construction Phase – Begin: 2016 | End: 2020
Amount Expended in FY 17/18: $6,300
Friant Road Widening
Friant Road Widening ID: E
Project Description
Widen Friant Road from Copper Ave to Millerton to a 4-Lane.
Funding
Measure C Extension
$4.12 Million
Total Cost
$4.120 Million
Progress
PROJECT COMPLETED
Begin: 2008 | End: 2009
Golden State Boulevard
Golden State Boulevard ID: F
Project Description
Corridor and Economic improvements to Golden State Boulevard from American Ave. to Tulare County line. Costs for Right-of-Way and Construction to be determined after the design portion is completed.
Funding
Measure C Extension
$6.83 Million
Progress
Design – In Progress
Environmental – Begin: 2013 | End: 2014
ROW and Construction to be programmed in the Long-Term Program which was under review at COG beginning 2016.
Total Project Cost to be determined after Design. 2021 scheduled completion.
SR 269 Bridge Improvement
SR 269 Bridge Improvement ID: G
Project Description
Construct a new bridge and channel on SR269 between SR198 and Huron to address seasonal road closures due to flooding. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$39.8 Million
Progress
This project’s funding and schedule will be programmed in the Long-Term Program which began the review process at COG in 2014.
Scheduled for 2021 completion.
SR 180 West I5 Extension
SR 180 West I5 Extension ID: H
Project Description
Route Adoption Study to extend State Route 180 West to Interstate 5 as a 3-Lane undivided highway. This $82.761 million project will be scheduled in the Long-Term Regional Transportation Program which will begin review in 2014.
Funding
Funding Source TBD
$82.76 Million
Progress
The funding and schedule for this project will be programmed in the Long-Term Program which began the review process by COG in 2014.
No funding available.
Mountain View Ave Widening
Mountain View Ave Widening ID: I
Project Description
Widen Mountain View Ave to a 4-Lane Divided road from Bethel Ave to the Tulare County line.
Funding
Measure C Extension
$15.22 Million
SLPP
$8.84 Million
Progress
Project I COMPLETED 2018
Design – Complete
ROW – Complete
Construction – Begin: 2012 | End: 2018
Academy Ave Widening
Academy Ave Widening ID: J
Project Description
Widen Academy Ave from Manning Ave to Industrial Way in Parlier. PROJECT COMPLETED 08/12 WITH $1.6 IN COSTS SAVINGS.
Funding
Measure C Extension
$1.95 Million
Progress
Project J COMPLETED 2012
Design/Right of Way – COMPLETED
Construction – COMPLETED
SR99 American Ave Interchange Improvement
SR99 American Ave Interchange Improvement ID: K
Project Description
Improve American Avenue Interchange on State Route 99. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$10.38 Million
Progress
The funding and schedule of this project will be programmed in the Long-Term Program which began the review process at COG in 2014. Scheduled for 2024 completion.
I-5 Interchange Improvement
I-5 Interchange Improvement ID: L
Project Description
Construct Interchange Improvement at the State Route 99 Interstate 5 Connection. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$18.24 Million
Progress
The funding and schedule for this project will be set in the Long-Term Program which began the review process at COG in 2014. Scheduled for 2027 completion.
State Route 41 Excelsior Expressway
State Route 41 Excelsior Expressway ID: M
Project Description
Widen Conventional 2-Lane Highway to 4-Lane Expressway
Funding
Measure C
$13 Million
STIP
$43 Million
SHOPP
$14.8 Million
Progress
Design – Begin 2024
ROW – Begin 2024
Construction – Estimated 2026